Water & Sewer Improvements Update 08/26/2025
🚧 Water & Sewer Improvements – Project Update 🚧
Construction continues on several streets in the Village as part of our ongoing water and sewer improvement project. Work is expected to continue at various locations through October 2025.
🔹 Iroquois St. (Lake St. to Ames St.) – Water improvements are complete and paving is finished. Final restoration is in progress.
🔹 Golf Course Dr. – Loop watermain has been placed. Crews are completing testing and final connections this week, followed by service connections.
🔹 Park St. (Buckley St. to Third St. and Third St.) – Water improvements are complete and paving is finished. Final restoration is in progress.
🔹 Charles St. – Preliminary sanitary sewer improvements begin the week of August 18.
🚦 Traffic Control:
Please be alert for construction workers in the project area.
Golf Course Dr. will be intermittently obstructed during construction.
Charles St. will be closed to through traffic.
We appreciate your patience and cooperation as these important improvements move forward. Thank you!