Water & Sewer Construction Update 09/05/2025

Our ongoing water and sewer improvement project continues through October 2025. Here are the latest updates:

✅ Iroquois St. (Lake St. to Ames St.) – Work complete, restoration touch-ups ongoing.
✅ Golf Course Dr. – Watermain and service connections complete, paving and restoration coming soon.
✅ Park St. (Buckley St. to Third St.) & Third St. – Work complete, restoration touch-ups ongoing.
🔨 Charles St. – Road pulverized, bypass pumping equipment set up starting September 8. Sanitary sewer installation begins September 8 and will continue for at least two weeks.

⚠️ Traffic Notes:

  • Golf Course Dr. will see intermittent closures.

  • Charles St. will be closed to through traffic during construction.

Please stay alert for workers in the project areas and thank you for your patience as we make these critical improvements to our community’s infrastructure.