Village Water & Sewer Projects Update 07/25/2025

Infrastructure improvements are continuing throughout the Village, with active work scheduled into October 2025. Here’s a quick look at what’s happening:

**Iroquois St. (Lake to Ames)**

  • Watermain and service installation is complete

  • Final connections and abandonment of the old main are underway

  • Stormwater upgrades and new culverts to follow

    • Road closed to through traffic**, intermittent closures for storm system work

    • Paving tentatively scheduled for August 11**

**Golf Course Dr. Loop**

  • Watermain is in place

  • Testing and system connections to be completed in the next two weeks

**Park St. (Buckley to Third) & Third St. (Meguzee Point to Park)**

  • Watermain installed and tested

  • Water service installations continue week of **July 28**

    • Road closures in effect**

    • Paving also targeted for August 11**

**Charles St.**

  • Sanitary sewer improvements begin the week of **August 4**

    • Road closed to through traffic** during construction

Please be alert and drive cautiously near all project areas. Thank you for your continued patience and support as we improve our community’s infrastructure!