Village Water & Sewer Projects Update 07/25/2025
Infrastructure improvements are continuing throughout the Village, with active work scheduled into October 2025. Here’s a quick look at what’s happening:
**Iroquois St. (Lake to Ames)**
Watermain and service installation is complete
Final connections and abandonment of the old main are underway
Stormwater upgrades and new culverts to follow
Road closed to through traffic**, intermittent closures for storm system work
Paving tentatively scheduled for August 11**
**Golf Course Dr. Loop**
Watermain is in place
Testing and system connections to be completed in the next two weeks
**Park St. (Buckley to Third) & Third St. (Meguzee Point to Park)**
Watermain installed and tested
Water service installations continue week of **July 28**
Road closures in effect**
Paving also targeted for August 11**
**Charles St.**
Sanitary sewer improvements begin the week of **August 4**
Road closed to through traffic** during construction
Please be alert and drive cautiously near all project areas. Thank you for your continued patience and support as we improve our community’s infrastructure!